Broadway Water Main Installation from Bryn Mawr to Thorndale is 90% Complete

Screen Shot 2016-04-13 at 11.50.10 AM

Installation of the water main pipe in phases 1 and 2 (Bryn Mawr north to Thorndale) is 90% complete. Pipe installation continues from Bryn Mawr to the first alley north.

Tomorrow and Friday the fire hydrants and sewers will be addressed, and next week the chlorination and testing begins.

Please note that there will be a planned water shutoff sometime next week. The Alderman’s Office will provide another update in this Friday’s email newsletter.

Please note:

All residents and businesses in the vicinity of the new water main will receive copies of the attached flyer from the Chicago Department of Water Management with instructions for flushing their plumbing to maintain water quality after service lines have been connected to the new water main.

FLYER: Chicago Department of Water Management Instructions for Flushing Plumbing